Page 1 of 2 12 LastLast
Results 1 to 10 of 12

Thread: barrman : Door Progress

  1. #1
    Join Date
    Dec 2003
    Location
    Giddings, Texas
    Posts
    7,731

    Default barrman : Door Progress

    Door Progress
    Post by barrman on Apr 14, 2006, 4:05pm

    During my "Jeep Pilgramage and East Coast Junk Yard Tour" I ended up with a set of really rusted doors. I finally started cutting on them.

    Here is the before pic with the markings of where I am going to cut.


    Here is the door after the cut.



    I will cut the other door tonight if possible and then start making the filler panels.

    What do you body work guys think is best.

    Make pieces that will fit but don't weld them on until the door is on the truck and in the closed position so it will be "square" all around?

    or

    Just weld it up and bend/beat it to make it fit later?

    Thanks

  2. #2

    Default robertcowan :

    Re: Door Progress
    Post by robertcowan on Apr 14, 2006, 7:23pm

    sure would be alot straighter if you weld it together fixed in place. also you should have installed braces before doing such a radical surgery. what are you making step through doors ?
    bob

  3. #3
    Join Date
    Dec 2006
    Location
    canby Oregon
    Posts
    359

    Default 503m715 :

    Re: Door Progress
    Post by 503m715 on Apr 14, 2006, 7:28pm

    I think I would have mounted door and aligned and then cut, but it will weigh less now.

  4. #4
    Join Date
    Dec 2003
    Location
    Giddings, Texas
    Posts
    7,731

    Default barrman :

    Re: Door Progress
    Post by barrman on Apr 14, 2006, 10:28pm

    The alignment problem isn't with the hinge to handle length dimension. It is with the twist. I cut the other do a few minutes ago and started playing with it. I am pretty confident I can make it work out ok off the truck. I will post pictures either way once I am done.

  5. #5
    Join Date
    Oct 2006
    Location
    Port Orchard, Wash.
    Posts
    4,572

    Default binfordm715 :

    Re: Door Progress
    Post by binfordm715 on Apr 14, 2006, 10:28pm

    Mind you I've never welded in my life so what do I know, but if you brace it in the finished position, won't the door still warp? On our cage legstands at work, they actually brace them skewed so when they weld the crossmembers to the legs, the unit straightens out. They know how much it will warp, and have compensated for the warpage when they brace it.

    Big pics, by the way!

  6. #6

    Default robertcowan :

    Re: Door Progress
    Post by robertcowan on Apr 14, 2006, 10:39pm

    what ya buildin out of the doors ? also do you have a mig welder ? if so spot weld it all over skipping around alot. this will help you with warping. you doing walk through doors like the m715 on trucks TV show ? bob

  7. #7

    Default jeepistdougiowa :

    Re: Door Progress
    Post by jeepistdougiowa on Apr 14, 2006, 10:42pm

    I would have throw a brace across the top before cutting, but now your best bet is to mount it and brace it, and then weld.

    Don't weld more than 1/2" in any one spot at a time. Do a star pattern alternating for the inside to outside with each 1/2" tack ending up with a series of welds around the perimeter 6" apart. Then continue to close the gaps with 1/2" welds in the same star/alternating pattern until done. That metal will crawl and twist even doing as I layed out, but keeping it cool with the wide spaced tacks is the best way to keep it to a minimum.
    I'd be very tempted to do the 6" spacing welds, then do the rest with epoxy. Big benifit is no heat/less warpage, but also you don't burn the paint off the inside where you can't repaint it.

  8. #8

    Default robertcowan :

    Re: Door Progress
    Post by robertcowan on Apr 14, 2006, 10:46pm

    1/2" welds are too much i think. no body man i know does anymore than a good tack. just my opinion not to stir up any problems. i,ve welded for 30 years all types and all metals. keep heat to a minumum. mig-mig or heliarc is best.

  9. #9

    Default jeepistdougiowa :

    Re: Door Progress
    Post by jeepistdougiowa on Apr 14, 2006, 10:49pm

    Less is always better in with this type of job, so no offense taken. I just know I used the 1/2 rule for some time and it works for me, but I'm no professional.

  10. #10
    Join Date
    Dec 2003
    Location
    Giddings, Texas
    Posts
    7,731

    Default barrman :

    Re: Door Progress
    Post by barrman on Apr 14, 2006, 10:53pm

    I am a picture 'tard on this new Zone. Jon changed my links to pictures. I am not sure how or why they ended up so big.

    I do have a MIG and I plan to do as several suggested as far as spacing the welds out and taking my time.

    I even started thinking about using the doors as storage areas or if nothing else, adding cup holders to the bottom.

    I and more importantly, Jennifer, liked the way the doors on Chad's truck looked on Trucks a few years ago. Two summers ago, another member did a really good job of using a still of that truck to make a dimensional drawing of the cut out section after I asked about it. I printed it out and have been waiting for a wasted set of doors to cut ever since.

    I thought about a brace on top or someplace else. I use a 7-1/2" grinder with a used cut off saw 14" disc to cut metal. Anything I welded on would get in the way.

    Also, I originally thought these would be step through type doors. Then I got the XZL's on and my truck is 2" higher. That doesn't sound like much, but I have almost fallen down several times now getting in and out. I imagine that once I get used to it I will be able to step through eventually.

Similar Threads

  1. gaskets under door handles, door panel clips, widow clip
    By Mudkaiser in forum Modified Tech
    Replies: 19
    Last Post: February 17th, 2024, 10:33 PM
  2. A little bit of progress
    By combat32 in forum Open Discussion
    Replies: 4
    Last Post: July 30th, 2008, 09:20 PM
  3. A little more progress
    By fisherman in forum Modified Tech
    Replies: 11
    Last Post: October 2nd, 2007, 09:43 PM

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  


Site Upgrade, Design Modifications & Administrative Support by:
Palm River Enterprises LLC, IT Solutions
President: Tom King, User ID=teking
This site is owned and operated by:
M715 Zone, LLC
President: Jon Schmidt, User ID=brute4c


If you have any suggestions, comments, problems or questions, contact:  brute4c@m715zone.com
Use of this site means you understand and agree to our TERMS OF USE

Copyright Notice:
This web site is subject to the protection of the copyright laws of the United States and other countries. Except for Personal Use Only, you may not modify, copy, distribute, transmit, display, perform, reproduce, publish, license, create derivative works from, transfer, or sell any information obtained from any part of the M715 Zone website without the prior written permission of M715 Zone, LLC. Written permission can only be obtained by contacting brute4c@m715zone.com

Copyright 1998-2024